Connection to High Voltage Grid
  1. The power supply shall start after:
    •    grid connection implementation;
    •    settlement of grid connection cost;
    •    delivery of the work for which the applicant is responsible, where applicable;
    •    installation of metering equipment;
    •    authorisation from the land owners crossed by the power line;
    •    transfer to E-REDES of the plot of land where the switching station is located, where applicable;
    •    licensing, surveying and authorisation of the coming onstream by the Directorate-General for Energy and Geology (DGEG) of:
             o the premise of the applicant;
             o the grid connection infrastructure.
    •    the signing of an operating protocol;
    •    inspection of the interconnection protections, if any;
    •     electricity supply contract with a supplier.